Design and Construction Management Capital Improvement Projects | Hollywood, FL (2022)

2nd Floor Library- Development ServicesDCM-19-001285Alex Iglesias2General Fund$6,200,000Interior completion of approximately 34, 000 SF of Shell Space constructed above the County Library at City Hall, to house Development Services including Building,

Planning and Zoning, Engineering, Code Enforcement and Community Development. After completion of the improvements and move of staff then remaining staff at the former library building can move into City Hall, former library building demolished and additional parking constructed.

The construction documents were submitted to the building department for approval on 8/17/22. The first round of comments were received. Fire, Structural, Electrical and Water disapproved. The revised drawings will be issued 9/7/22. Kaufman Lynn submitted their Pre-GMP project deliverables on 8/23/22. City staff will meet to discuss on 9/1/22. Broward County negotiations continue in reference to the ILA Amendment Draft.Hollywood Boulevard Landscaping- City Hall to Dixie HwyPW 13-015Dana Nelson2,3C.I.P. – Broward MPO Grant$1,200,000Install landscape, irrigation and miscellaneous street furniture to perform City grant share of complete streets project after FDOT completes project.Construction scheduled to commence in October 2022.Avant-Garde Sidewalks (Grant)EN 17-004/DCM-19-001121Luis Lopez2,3C.I.P.-State of Florida Safe Routes to School Grant $983,393 for FY 2020-22 for constructionNo contract for construction yet.Construction of approximately 2.5 miles of new concrete sidewalks and swale regrading near the Avant-Garde Academy, Broward. North Central sidewalks, completion of one side of the street from 22nd Ave to 24th Ave, from Grant St to Wilson St.On August 31 the City Commission awarded a construction contract in the amount of $765,407. In the same meeting a Construction Engineering and Inspection contract was also awarded to an Engineering consultant. This consultant will assist with daily inspections, project management and FDOT reporting required by the grant funding agreement. Construction activities are anticipated for mid October 2022.David Park Tennis Center Re-roof - 108 N 33rd CtDCM-19-001278 / PW 18-012Karyn Sashi3Re-roofing of the Tennis Center pro shop.

The City of Hollywood is pleased to announce the completion of the David Park Tennis Center roof replacement project. On February 7, 2022, the construction to replace the existing roof began. The roof was severely damaged, due to termite and water intrusion over time. After two months of construction, the roofing project is now complete.

Renovations of the men’s and women’s interior restrooms will begin shortly. With the drawings in permit process, DCM will be going to Commission for the approval of the Contractor’s quote.

Design District SignsCM 16-020Karyn Sashi4Two new lighted monument signs for newly created Design District. Two signs to be installed in the median of N. 29th Avenue, between Sheridan Street and Stirling Road.Project completed.Hollywood Boulevard/SR7 Mobility HUB ( Grant)DCM-19-001241Rudy Damas6$900,000 Broward MPO Sub recipient Agreement, $50,000 City Funds$950,000Local Agency agreement with Broward MPO to construct Mobility Hub ImprovementsOn October 19, DCM will present and recommend the project to the City Commission to approve the Construction contract for the low-responsible bidder.Stan Goldman ParkDCM-19-000142Karyn Sashi3Park Impact Fees$167,120Phase II on-going park enhancements. Community meetings held to determine desired improvements for phase II. Pickle-ball courts, restroom renovations, skate park renovations, security lighting, asphalt trail repaving, drainage, and security stations, received approval of the community.Restroom quotes received and are being submitted to Procurement for review and approval. Pickleball and Skate Park purchasing process being discussed with Procurement. Enlarging and repaving of the asphalt pathway is in permitting with Broward County.
SR7 Linear ParkDCM-19-000144Rudy Damas4,6$300,000 Park Impact Fees$300,000Construction of Playground at the FDOT property at the SE corner of Johnson St and SR7. Installation of pedestrian scale lighting along linear park and pedestrian access across drainage retention area at Taylor St and Pierce St.Construction of the playground at the SE corner of Johnson St and SR7 is complete, pending fence installation. On the August 31st meeting, the City Commission approved a Resolution to award the construction contract to MBR construction to complete the remaining work of the Linear Park Improvements.Tree Mitigation

PRESENTATION: OCT. 26 PUBLIC MEETING

DCM-19-000216Rudy Damas1,3,4,5,6$580,000 total estimated cost of tree plantingsAn estimated 1210 new shade trees as will be planted. This project will meet the requirements of the City's agreements with the Florida Department of Transportation, whereas they would construct bicycle lanes and road improvements to 14 the Avenue, Polk Street, Park Road , and 56 Avenue and the City would take on the responsibility of the mitigating the lost trees along those projects, per Broward County.On September 21, 2022, DCM will present and recommend the project to the City Commission to approve the Construction contract for the low-responsible bidder.Bike Lane- 56th AveDCM-19-001272Rudy Damas4,6$140,000Bike Lane Projects supported and requested by the City and funded by Broward County MPO. The bike lane projects are being constructed by FDOT. The City is responsible for any tree removal mitigation.This project was completed on Thursday, April 7, 2022, and the project corridor has now been returned to the City.Bike Lane- 14th Ave.

PHOTOSDCM-19-001271Rudy Damas1$20,000Bike Lane Projects supported and requested by the City and funded by Broward County MPO. The bike lane projects are being constructed by FDOT. The City is responsible for any tree removal mitigation.FDOT Bike Lane improvement Project completed.Bike Lane- Park RoadDCM-19-001273Rudy Damas3,6$140,000The bike lane projects are being constructed by FDOT. The City is responsible for any tree removal mitigation. This project includes improvements on several streets around Park Road. FDOT Bike Lane improvement Project completed.Bike Lane- Washington Street, 72nd Ave.DCM-19-001270Rudy Damas5,6$150,000Bike Lane Projects supported and requested by the City and funded by Broward County MPO. The bike lane projects are being constructed by FDOT. The City is responsible for any tree removal mitigation.The FDOT Bike Lane improvement Project is currently installing drainage structures on 72nd and by the end of next week will transition to Washington St.Johnson St Broward MPO CSLP ( Complete Streets and other Localized Initiatives) match 14th Ave to 35th AveDCM-19-000087Luis Lopez2,3$282,601 City Funding, $1,469,007 MPO/ FDOT funding$1,751,608Broward MPO 2019 CSLIP Cycle 3 Award for 2025 Funding and construction. Local Agency Project (FDOT grant) project to be constructed by the City, together with the installation of water and sewer lines. Grant includes pedestrian scale lighting, 35th Ave to 14th Ave, Sharrow Bike Lanes, Pedestrian Railroad crossing at the South Side of SFRTA railway west of I-95. Installation of sidewalks missing in the south side, missing segment west of 28th Ave in the north side, roadway resurfacing from 31st to Dixie Hwy, drainage improvements, ADA improvements ramps by the City.The Design Phase of this project will start in 2023.Surf Road at Balboa St Erosion

PHOTOS

DCM-19-001293Luis Lopez1Gas Tax Fund$157,140Reconstruction of Surf Road and shoreline protection treatment to protect this section of roadway, washed out during October 2019 king tide events.On July 6, 2022 meeting, the City Commission awarded a construction contract in the amount of $439,679. Contract has been executed, Notice to Proceed issued to the contractor, and construction is set to commence early November. Florida Department of Environmental Protection limit construction activity during marine turtle nesting season, which runs from May 1st through October 31st.US 1 CSLIP, Sheridan St to Pembroke RoadDCM-19-001361Jose Cortes1,2
Broward Metropolitan Planning Organization CSLIP projects to be constructed in early 2022 by FDOT. Scope includes resurfacing, creating a 4’ bike lane, adding pedestrian scale lighting, LED lighting upgrades, stamped asphalt crosswalks at signalized intersections, replacement of concrete sidewalk with pavers from Fillmore to Monroe St, excluding Young Circle. Landscaping to follow by the City.City staff is coordinating with the Florida Department of Transportation.Rock House Vollman Park

PHOTOS

DCM-19-001143Alex Iglesias3Park Impact FeesEvaluation of existing rock house structure.Cartaya & Associates Architects submitted 50% construction documents on August 24, 2022. They continue to work on 100% CD’s and are projected to be ready to submit the permit set for approval on September 15, 2022.Lifeguard/First Aid Beach Station outside the CRA limits

PHOTOS

DCM-19-001269Karyn Sashi1C.I.P.$823,880Replacement of two first aid stations and six lifeguard towers outside of the Beach CRA district.

Lifeguard Towers:
​ •DeSoto Street

​ • Perry Street

​ • McClelland Street

​• Douglas Street

​ • Sheridan Street

• 3801 S. Ocean Drive

First Aid Stations:
​ • Meade Street
​ • Simms Street

The manufacturer, Post and Beam, has delivered all eight lifeguard towers to the beach. All of the towers are in their final locations and operational. The manufacturer and roofer are working on final punch list and closeout items and will be complete by the end of September.

Hollywood Blvd Traffic Calming from N./S. 28th Avenue to E. of City Hall Circle

DCM-19-001124Heather Guenot2,3$85,000

(Study Phase Only)

Rehabilitation of Hollywood Blvd. from I-95 to the East side of City Hall Circle. Project includes pavement rehabilitation, bike lane widening, replacement of paver crosswalks, sidewalk repair and ADA upgrades, lighting improvements, and landscaping improvements (shrubs and groundcover only).The study phase for this project is complete. Design Consultant Craven Thompson & Associates, Inc. completed the Basis of Design Report and concept plans in June 2021. The City has used these plans to re-apply for Surtax funding for Design and Construction from the Broward Metropolitan Planning Organization (MPO) for the design phase of this project. Unfortunately, the project was not selected for MPO funding in the 2022 cycle.Hollywood Blvd at 26th Ave. Traffic Signal Mast Arm ReplacementDCM-19-001125Heather Guenot3$180,000Replacement of 3 existing Mast Arms, one at the Northeast corner of Hollywood Blvd/N. 26th Ave, two at the Southwest and Southeast corners of Hollywood Blvd/S 26th Ave. Includes electrical work, geotechnical investigation, and temporary signals if required.The Design Consultant for the project, Chen Moore & Associates, received City of Hollywood ROW Permit approval. The project went out to bid in June, and bids were received in July. The bids have been reviewed and a recommendation made for award. The construction contract is anticipated to go to City Commission for approval on September 7, 2022.New Police Headquarters Radio TowerDCM-21-001523Heather Guenot6CIP/ARPA$1,195,619Design and Construction of a Radio Tower adjacent to the New Police Headquarters building. The radio tower will be used for both the Police Department and Local Government Radio.The Project is currently in the Study Phase; the consultant is currently assessing the City’s needs and developing radio tower options to fit these needs. This project is being developed in close coordination with the New Police Headquarters project, and will be located adjacent to the new building. The project was reviewed at the PACO Planning Department meeting on May 9, 2022.Five Bridges RepairsDCM-22-000081Heather Guenot3 & 4CIP$238,100Design and Construction of Repairs to the following bridges:

Bridge ID 866301: N. 29th Avenue at the C-10 Spur Canal, 0.5 miles North of Sheridan Street

Bridge ID 866302: Sanders Street at the C-10 Spur Canal, 0.3 miles E of Casper Ct.

The City is in the process of procuring a Design Consultant for this project from the pool of consultants under Continuing Services Agreements with the City.

You might also like

Latest Posts

Article information

Author: Melvina Ondricka

Last Updated: 07/31/2022

Views: 5704

Rating: 4.8 / 5 (48 voted)

Reviews: 87% of readers found this page helpful

Author information

Name: Melvina Ondricka

Birthday: 2000-12-23

Address: Suite 382 139 Shaniqua Locks, Paulaborough, UT 90498

Phone: +636383657021

Job: Dynamic Government Specialist

Hobby: Kite flying, Watching movies, Knitting, Model building, Reading, Wood carving, Paintball

Introduction: My name is Melvina Ondricka, I am a helpful, fancy, friendly, innocent, outstanding, courageous, thoughtful person who loves writing and wants to share my knowledge and understanding with you.